Below is Main Street Redevelopment Project Update #8.

OrangeSidewalksJune18sConstruction Activity, June 21-June 25

  • Pour concrete pavement on Orange Street.
  • Remove sidewalk, curb and gutter, pavement and driveways on Main Street from Base Street to Genesee Street and on Base Street.
  • Install watermain on Main Street from Genesee Street to Cherry Street.

 

 

 

 

 

Work Completed June 14 – 18

  • Concrete pavement was installed on Market Street east of Orange Street and on Main Street west of Orange Street.
  • ADA ramps on the west side of Orange Street at Main Street were poured.
  • The island for the Post Office was poured.
  • Sidewalk on Orange Street was completed.
  • Insertion valves were installed and the existing watermain was lowered, at Main Street and Base Street.
  • Storm sewer was completed at Base Street and Main Street and Base Street and Market Street.

Street Closures

  • Orange Street, from Market Street to U. S. Route 30, will be closed.
  • Main Street from Orange Street to Genesee Street will be closed.
  • Base Street from U. S. Route 30 to Market Street will be closed.
  • Main Street from Genesee Street to Cherry Street will be closed from 7:00 a.m. to 5:30 p.m., when the contractor is working on the watermain.